National Parks & Wildlife Service - North Chowan Landslip Remediation

Nov 12
2 min read

Kyogle Earthworx successfully completed a comprehensive range of civil construction, earthworks, road rehabilitation, drainage and slope stabilisation activities associated with the project.

The scope of works included the following:

1. Bulk Earthworks

  • Construction of an access track to the base of the fill area.

  • Stripping and stockpiling of topsoil for reuse on site.

  • Clearing and mulching of existing vegetation.

  • Excavation and removal of slip material.

  • Preparation of boxed-out areas for placement of rock fill.

2. Bulk Earthworks Within the Road Reserve

  • Clearing and mulching of vegetation.

  • Excavation and removal of spoil material.

  • Preparation of boxed-out areas for filling and compaction.

  • Pulling back, trimming and reshaping of existing batters.

  • Preparation of pavement subgrade for roadbase placement.

3. Construction of Road Pavement Within the Slip Area

  • Supply and delivery of roadbase materials.

  • Placement, grading and shaping of road pavement materials.

  • Watering and rolling to achieve the required compaction and pavement finish.

4. Filling and Stabilisation of Slip Area

  • Supply, delivery and placement of 1000 mm minus rock fill.

  • Placement of rock fill within prepared areas to reinstate and stabilise the slip-affected section.

5. Drainage and Pipe Works

  • Supply and installation of reinforced concrete pipes (RCPs).

  • Construction and installation of drainage inlet pit.

  • Construction and installation of drainage headwall.

6. Supply and Placement of Gabion Baskets

  • Supply and installation of gabion baskets as part of the slope stabilisation and erosion protection works.

7. Stabilisation of Drains

  • Completion of drainage stabilisation works to minimise erosion, manage stormwater runoff and protect the rehabilitated areas.

Project Outcome

Kyogle Earthworx successfully delivered the required civil construction works, incorporating bulk earthworks, road pavement reconstruction, rock fill placement, drainage infrastructure and erosion protection measures.

The completed works contributed to the reinstatement and stabilisation of the slip-affected road section, improved stormwater management and provided long-term protection against further erosion and deterioration.


 
 
 